Finish Drains and Final Inspection

Date: June 8  - Juneteenth, 2026

I called Monday for final inspection on the following day June 9. Inspector had no issues with plumbing,  electrical, framing, deck, stairwell or my loading dock setup. The only concern was the rock threshold outside the shop entrance door which was a platform without any railing. His concern was that someone exiting the building could walk off the edge. He requested that I build a simple railing protecting the drop-off, with a horizontal board a foot or two off the ground to keep someone's foot from sliding under the railing. Seemed like reasonable to me as he was not asking for a "real" railing (6" maximum gap between pickets or slats) around this small drop-off. 

The problem was how to build the rail inside the edge of the rock platform. As seen in the picture below, the rock wall on the outside corner stepped out so I couldn't dig a fence post hole there. Maybe attach it to the rock? I went to the hardware store an bought a couple of brackets.

 

After sleeping on it I decided to break out the grinder which still had the tile cutting blade on it. Testing the tile blade on the rock revealed that it cut easy as butter. 

 

I didn't think it would be that easy. I started to work on creating a flat spot: 

 

Attaching the brackets to the rock with blue TapConn screws didn't work at all. You can't screw them in, even when tap hole is size specified - they just don't "tap" the rock. I got to say those things are pretty worthless as they have never worked for me in concrete either. Luckily my odds-and-ends hardware collection included some masonry inserts. Using the Lenox diamond tipped tile drill bits to create the right size hole in the rock, I was able to seat a plastic insert then use stainless screws which were really stout.

 

 

Then complete the required railing:

All I had to do was send the pictures to the inspector on June 12 and he completed the "Certificate of Compliance" (not "Certificate of Occupancy" since this was not a residence).

 

 

I had to call to remind him but on June 17 I got the certificate.

Meanwhile although my big Rotary dinner was planed for just a week hence on Juneteenth, I wanted to dig up the driveway one more time to finish the drains. I had purchase the heavy duty storm drain box (seen below) and grate from Ferguson's "Water Works" store in Asheville several months prior. The first task was to find the old drain box which I had covered with boards and a foot of dirt when we started the excavation the previous year. The boards were just about where I expected them to be:

 

After the old pipe was uncovered: 

 

My plan was to use that box as the merge point for four different drains:

  1. The pipe running from the backfill and under the garage slab which drained the constant flow of water from the back of the building. This was described in great detail in the Footer Excavation post.
  2. The pipe coming from the root cellar floor drains.
  3. A new pipe to drain the roof gutter downspout on the southwest corner of the building.
  4. A new pipe to complete the footing drain which came around that same corner of the building.

The point of joining all these pipes at an open-top vault that was on the other side of the driveway was that there would be no possibility of backflow if the merged pipe got blocked for some reason. If the pipes are just joined underground then a blockage might cause roof run-off during a storm to back up into the root cellars and flood them. 

This photo documents the digging for pipe #4. I found that there was water running continuously from the footing drain gravel:

And this photo documents pipe #1and the stub coming through the footing of pipe #2: 

Another day of digging and I'd pretty much filled the driveway with piles of dirt:

 

The following day I finished the digging but the water had been seeping in overnight as seen in this walk-through:



 Working late into the evening and early the next morning of June 14 I got some of the pipes glued up and connected:

 

Based on what I learned from the sewer pipe install, I taped an old extension cord over the length of the pipes to allow the power company to detect and mark the location 

 

Filled in enough of the ditch to allow driving in and out:

 

 For pipes 3 & 4 I relaxed my standard to have the footer drain merge underground with the downspout drain as you can see in the right branch below. To make it just a bit better I ran the footer drain pipe so that dumps into the top of the downspout drain. This means to have the downspout water go back up to the footer area would take a lot of pressure.

 

And by the following day I'd covered the whole thing up and tried to restore whatever gravel I'd scraped off before beginning the digging. 

 

Still need to get a load of gravel to cover up all that dirt, but this was good enough to folks get in and out of the garage for the Rotary Dinner.

 

No comments:

Post a Comment