Dates: May 6 - June 2, 2026
In my arrangements with the tradesmen, it was understood that I would be procuring all the plumbing and electrical fixtures. So for many months I had been YouTubing, Googling and shopping online as well as at brick-and-mortar stores for fixtures.
I had questions on the tiling requirements for the tub fixtures so I sent a text to request more info from Nick Hagan, the plumber. I've found that there is always a huge context gap when talking with these professionals because for them it is all standard ("of course that is the way it works"). Whereas I am cluttering my mind with all the ways it could be done, and when I ask questions to try to narrow it down they don't understand what I'm asking. Eventually I resolved that the best way to ask a question is to take a picture of the product and say "Is this it?"
Here is a montage of pictures in my phone related to my research into these fixtures: 
Standard practice is to do plumbing before electrical. As soon as we started tiling the bathroom floor I projected that it wouldn't take more than two weeks so I asked Nick the plumber to schedule me, and he said May 4. Got to give lead time or else you risk lengthy intervals of nothing happening. That day didn't see any action beyond a phone call where we discussed what I had on hand for him to install. Good thing because we discovered that I needed to have fancy connectors for the on-demand water heater which would allow it to be isolated and flushed. Here is the kit with hot, cold and pressure relief fittings:
It turns out that access port turned out to be mighty handy about a month later - but more on that in a later post!
Nick arrived on May 6 after working since 5 AM on an emergency repair, so didn't get a whole lot done besides hooking up the tub drain. However he sized up the remaining work and said he'd be back in a week to finish it. I decided to test that tub drain and it was a flop - leaking water all over the stairs below. A week later he and his helper Oscar were back at it and they got most of the rest done. Then Oscar came alone the following day and finished it up including rework of the tub drain. One of the complications was that at the time of rough-in I was planning to re-use the pedestal sink from the temporary bathroom I'd built when we first moved here. Nick had looked at it an routed the pipes accordingly. But more recently I decided that a vanity would be more functional by providing much needed cabinet space. Unfortunately that meant the pipes had to be offset twelve inches and that took some wrangling.
The financial aspect was a bit odd because Nick had collected for the entire job, rough-in and finish, at the time of completed rough-in. So my understanding was that the bill was paid. He wanted to bill me for the hours. After reviewing the original deal messages with him, and in light of the changes and additional work needed for the sink, we agreed on $525 due.
Nick called in the permit for the plumbing final inspection but I'd already verified that the building inspector would only come out after they'd received the final inspection request for all the building aspects.
Nick's dad Erik followed on May 22 to finish the electrical. I noticed this weather proof outlet was mounted on the siding piece we'd installed but stuck out too much for the door opening (and I thought it my problem to fix that one as one could claim that the siding was at fault).
Later I redid the siding and bought a new box giving a streamlined outlet (and a cracked board):
One day saw about half the work done. No complaints on most of the work:
I didn't have the required switch plate on hand for this one.
A week elapsed before Erik made it out again to work on the shop lights:
And - oh hey! - you can see above another result of my shopping efforts: the loading dock door safety net. Erik had pointed out that the inspector wasn't going to be happy with the double doors that just opened out into thin air with a 3 foot drop (code would normally specify a deck and railing). Since I wanted to be able to back right up to the building for my loading dock, I searched far and wide for a net to protect against accidental egress. This one came from a small online safety equipment store in Ohio.
The bathroom vanity also caused problems for the electrical. Because in preparing for the light over the vanity the rough-in hadn't planned for the type of light I bought, so there was no box to mount the light on. I rectified the issue by cutting back the sheetrock to solid support then installing some plywood backing:


After all the fixtures and breakers were installed,
Erik completed the connection of the shop to the 400 amp service down the hill. The wires for this were all placed months before, but had been sitting outside waiting for this day to come:

However he did not energize the shop because that should wait for final inspection, and he's a licensed electrician so sticks to the book on these things. We settled the final bill, which was the remaining half of his original prices plus extra materials and change order's I'd made. He was very meticulous, dare I say old-school, in tracking exactly what everything cost him and providing the detail.
The following day, not being a licensed electrician, I took the liberty of testing the electrical. I turned off all light switches, breakers and the main in the garage load center, then energized the line up from the 400 amp service. Next I switched on the main the garage load center then tested each circuit independently. When I got to the "Shop Lights" circuit I went upstairs and when I turned on the light nothing happened. I went back to the load center and saw that the double-pole 15 amp breaker was flipped. I pushed it back and it insisted! Bad news - there must be a short!
Turning the power off again, I traced the blue double-pole line which went directly the main light switch box in the shop. I pulled the wires out and saw what you see below.
I took the picture thinking I'd send it to Erik so he would know it had a problem. But as I studied the situation, looking at what was connected to what, the error became clear to me. One pole's supply wire had been directly connected to a circuit powered by the other pole's supply wire. So that was a very direct short circuit, and that is why we install breakers. Otherwise that whole thing would have melted and started a fire in an instant! I also learned that if you make such a mistake in your wiring you fry the circuit breaker itself, because now you couldn't even push it do the On position.
There was a lot of branches in this lighting circuit so I trace the various wires assiduously and labeled them with a marker. "Bathroom Overhead, Bathroom Vanity, Stairs, Upstairs Porch, Shop Door, Shop front, Shop back, etc". From the various wire nuts and labels that Erik had used, I deduced the circuit design. He was planning on using one pole for the front of the shop and the other for the back of the shop, then divvy up the remaining branches between the two poles. He just made a mistake in which wire was which.
So I fixed that, then borrowed the other 15 amp double-pole circuit breaker to test it again. And I saw the light:
Here is a walkthrough of the bathroom with all fixtures and lights as of June 2nd. You can see that custom walnut under the vanity light: